Dear experts:

 

We are implementing SAP Solution Manager ChARM for ECC and BI and we have almost the whole solution implemented, however we have a scenario on that we need your advice. The scenario in detail is described below:

 

1. We have an OT with the A, B and C objects belonging to a normal change with transport request TN01, and the transport request linked to those change was successfully imported to quality system.


2. An urgent change is created and objects A, D are related to this change, with transport request TU02. The changes are successfully imported to quality system, and certification team did not report any issues on testing process.

 

3. The transport of the urgent change transport request is authorized to be imported on productive system

 

Is there any way to alert about the object that is in both change documents before the transport request is imported to production system?

 

What is the best practices recommendation about the above scenario?

 

Thanks in advance.